「AP過去問 令和6年度春期 午前 問18」の版間の差分
(→回答・解説) |
(→回答・解説) |
||
41行目: | 41行目: | ||
<script></yjavascript> | <script></yjavascript> | ||
1重化のときは4秒×4タスクで16秒かかりますが、 | |||
<span class="nonsquare-number">1<sub style="color:white;">0</sub></span><span class="nonsquare-number">2<sub style="color:white;">0</sub></span><span class="nonsquare-number">…<sub style="color:white;">0</sub></span><span class="nonsquare-number">…<sub style="color:white;">0</sub></span><span class="nonsquare-number">15<sub style="color:white;">0</sub></span><span class="nonsquare-number">16<sub style="color:white;">0</sub></span></br> | <span class="nonsquare-number">1<sub style="color:white;">0</sub></span><span class="nonsquare-number">2<sub style="color:white;">0</sub></span><span class="nonsquare-number">…<sub style="color:white;">0</sub></span><span class="nonsquare-number">…<sub style="color:white;">0</sub></span><span class="nonsquare-number">15<sub style="color:white;">0</sub></span><span class="nonsquare-number">16<sub style="color:white;">0</sub></span></br> | ||
53行目: | 53行目: | ||
その差は16-9で7秒です。 | |||
したがって | |||
<span style="background:linear-gradient(transparent 75%, #7fbfff 75%); font-weight:bold;"> | |||
イ</span> | |||
が答えです。 | |||
2025年1月30日 (木) 02:20時点における版
AP過去問 令和6年度春期 午前 問17前の問題へ
AP過去問 令和6年度春期 午前 問19次の問題へ
問18(問題文)
複数のクライアントから接続されるサーバがある。このサーバのタスクの多重度が2以下の場合、タスク処理時間は常に4秒である。このサーバに1秒間隔で4件の処理要求が到着した場合、全ての処理が終わるまでの時間はタスクの多重度が1のときと2のときとで、何秒の差があるか。
ア 6
イ 7
ウ 8
エ 9
回答・解説
1重化のときは4秒×4タスクで16秒かかりますが、
1020…0…0150160
1121…0…03444
2重化されているときは以下のように9秒で処理可能です。
102030405060708090
1121314113233343
001222324214243444
その差は16-9で7秒です。
したがって
イ
が答えです。
AP過去問 令和6年度春期 午前 問17前の問題へ
AP過去問 令和6年度春期 午前 問19次の問題へ